Endeavour Silver Completes Feasibility Study for the Pitarrilla Project Delivering After-Tax NPV of $736 Million; Study Highlights a Long-Life, Low-Cost Growth Opportunity with Significant Free Cash Flow Potential

Management will host a webcast and conference call at 9am PCT (11am ET) on Friday, November 20, 2026

[PDF] Press Release: Endeavour Silver Completes Feasibility Study for the Pitarrilla Project Delivering After-Tax NPV of $736 Million; Study Highlights a Long-Life, Low-Cost Growth Opportunity with Significant Free Cash Flow Potential
[PDF] Press Release: Endeavour Silver Completes Feasibility Study for the Pitarrilla Project Delivering After-Tax NPV of $736 Million; Study Highlights a Long-Life, Low-Cost Growth Opportunity with Significant Free Cash Flow Potential

Vancouver, Canada, 20.11.2026 (PresseBox) -

Low-Cost Production Supporting Long-Term Growth: Planned annual production averaging 7.5 Moz AgEq(1) over an 18-year mine life, with 73% of revenue from silver, positions Pitarrilla as a cornerstone growth asset

Significant Project Value: Projected after-tax NPV (5%) of US$736 million with an initial capital(2) investment of US$585 million

Strong Cash Flow Generation: Pitarrilla is expected to generate substantial after-tax operating cash flow(2) of US$2,443 million over its operating life, supported by competitive operating costs and robust commodity price assumptions

Endeavour Silver Corp. (“Endeavour” or the “Company”) - https://www.commodity-tv.com/ondemand/companies/profil/endeavour-silver-corp/ - is pleased to announce the results of a Feasibility Study (the “Study” or “FS”) for its Pitarrilla Project (“Pitarrilla” or the “Project”), located in Durango State, Mexico. All amounts are in U.S. dollars unless otherwise stated.

The Study evaluates the development of a mechanized, ramp-access underground mine focused on the Project’s sulphide mineralization and high-grade core. The proposed operation is designed at 4,000 tonnes per day (tpd) of processing capacity and would produce silver-lead and silver-zinc concentrates using conventional crushing, grinding and flotation, with filtered tailings planned for dry-stack facility.

The Study represents an important milestone in advancing Pitarrilla toward a development decision. The Company will file a technical report supporting the Study on SEDAR+ within 45 days of this news release, in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”).

(1) Silver equivalent ratios are calculated using 41 silver oz to 1 lead tonne; 55 silver oz to 1 zinc tonne

Feasibility Study Highlights

Strong Project Economics: The project delivers an after-tax Net Present Value (NPV) of $736 million at a 5% discount rate and after-tax Internal Rate of Return (IRR) of 16.37%, based on FS assumptions of $50.00 per ounce (oz) silver (Ag), $2,028.23/tonne (t) lead (Pb) and $2,733.70/t zinc (Zn)

Large-Scale, Long-Life Production: Planned average annual production of approximately 5.4 Moz of silver, 13 kt of lead, 29 kt of zinc and 7.5 Moz silver equivalent(1) (AgEq) over an 18-year mine life (LOM), highlighted by average annual production of 7.9 Moz AgEq for the first 5 years of full operation

Key Permits Supporting Development: Key permits are in place for water use and discharge, explosives, change of land use, development and underground mining. Additional approvals and amendments remain outstanding, including the Tailings Storage Facility Permit (TSF)

Resilience at Lower Silver Prices: Pitarrilla has an estimated break-even silver price below $30 per ounce, compared with the base-case silver price of $50 per ounce, providing a margin against lower silver prices while maintaining leverage to higher silver prices

Capital Investment for Long-Term Growth: Planned initial capital(2) of approximately $585 million, including $65 million of contingency, with sustaining capital(2) of approximately $119 million over the life of mine. Approximately 16.7 kilometres of development over the LOM provides access to over 25 million ore tonnes

Low-Cost Production Supporting Cash Flow Potential: Planned LOM average cash costs(2), net of by-product credits, of $12.66 per payable silver oz and mine-site all-in sustaining costs(2) (AISC) of $15.06 per payable silver oz support a low-cost operating profile

Well Positioned to Fund Construction: Endeavour expects to fund the majority of construction of Pitarrilla through a combination of cash on hand and cash flow from its operating mines, providing flexibility as the Project advances toward a development decision

Mechanized Underground Mining: A ramp-access underground mine is designed to support planned production averaging approximately 4,000 tpd, utilizing long-hole stoping and development in ore

Conventional Processing: The processing flowsheet includes crushing, grinding and flotation, followed by concentrate thickening and filtration. Filtered tailings are planned for storage in a dry-stack facility

Established Infrastructure and Access: The Project benefits from year-round road access, connections to power and water infrastructure and existing exploration and contractor camps

Significant Opportunities to Enhance Value: Resource conversion, exploration upside, open-pit optionality and further mine-plan, processing and cost optimization offer additional potential to enhance long-term value

“We are excited by the strong Feasibility Study results, which mark a major milestone for Pitarrilla and highlight a compelling opportunity for Endeavour’s next phase of organic growth,” commented Dan Dickson, Chief Executive Officer. “With an anticipated initial 18-year mine life, substantial silver production and an extremely attractive operating cost profile, Pitarrilla has the potential to become a cornerstone asset that delivers lasting value for our shareholders.”

Resilient Economics with Silver Price Upside

Pitarrilla demonstrates resilient project economics across the range of silver prices evaluated, with significant leverage to higher silver prices and an estimated break-even silver price below $30 per ounce. At the base-case silver price of $50 per ounce and a 5% discount rate, the Project delivers an after-tax NPV of $736 million and an after-tax IRR of 16.37%. The sensitivity analysis indicates that project value and returns are most responsive to metal prices and comparatively less sensitive to changes in initial capital costs, highlighting Pitarrilla’s strong exposure to silver-price upside.

Location and Access

Pitarrilla is located within the Municipalities of El Oro and Inde, on the eastern flank of the Sierra Madre Occidental mountain range in the central part of Durango State, Mexico. The city of Durango, the capital of Durango state, is located 160 kilometres south of the property and the major city of Torreón 160 kilometres to the east.

Pitarrilla is accessible by regional roads. Planned primary access follows approximately 47 kilometres of existing roads, with secondary access via El Palmito. Required upgrades include a permanent bridge over the Nazas River, approximately 11 kilometres from the property.

Property, History, Geology, Mineralization

Pitarrilla is formed by 5 contiguous mineral concessions entitled to Minera Pitarrilla S.A. de C.V. (“Minera Pitarrilla”) and covering a total area of approximately 4,950 hectares. Minera Pitarrilla is a Mexican corporate entity, and a wholly-owned subsidiary of Endeavour. 

The Sierra Madre mountain range preserves remnants of one of Earth’s largest accumulations of intermediate to felsic volcanic rocks, formed in a calc-alkaline magmatic arc during the Eocene to early Miocene, approximately 52–25 million years ago. This volcanism intermittently generated numerous medium- to high-level hydrothermal systems enriched to varying degrees in Ag, Au, Pb and Zn, including epithermal systems in the major Mexican silver districts of the states of Guanajuato, Zacatecas, Durango and Chihuahua. Pitarrilla’s silver-lead-zinc mineralization lies within the Central Mexican Silver Belt, a metallogenic province encompassing these districts. 

Endeavour purchased Pitarrilla from SSR Mining Inc. (SSR) for $70 million in 2022, consisting of $35 million in common shares and a further $35 million in cash or in common shares at the election of SSR and agreed to by the Company, and a grant of a 1.25% NSR royalty.

Mine Plan and Production Profile

Pitarrilla is planned as a mechanized, ramp-access underground mine capable of supplying approximately 4,000 tonnes per day to the processing plant. The current design contemplates a mining mix weighted toward transverse and longitudinal long-hole stoping, supplemented by development in ore. The mine plan is expected to target the sulphide mineralization, including Manto Pitarrilla and associated feeder structures. The readily accessible Manto Pitarrilla deposit configuration supports an efficient mine layout with relatively limited underground development required over the LOM. Approximately 16.7 kilometres of total development is planned, comprising 5.4 kilometres during the initial years and 11.3 kilometres of sustaining development thereafter, providing access to the deposit while supporting operating flexibility and efficient, low-cost mining. The current mine plan includes stockpiling over 600,000 tonnes of ore during the construction phase.  

Processing and Infrastructure

The proposed 4,000 tpd process plant is expected to include crushing, a grinding circuit incorporating a primary ball mill and a semi-autogenous grinding (SAG) mill, flash, rougher, scavenger and cleaner flotation, concentrate thickening and filtration, and a tailings filtration plant. Filtered tailings are planned to be placed in a dry-stack storage facility. Pitarrilla benefits from year-round road access and an established project footprint with power and water access, exploration infrastructure, contractor facilities and regional access to an experienced workforce.

Capital Investment, Operating Costs and Cash Flow

Initial capital(2) to develop Pitarrilla is estimated at $585 million and is expected to be incurred over a 30-month construction period. Cumulative sustaining capital(2) is estimated at $119 million. Sustaining expenditures are expected to be front-end loaded, as the readily accessible Manto Pitarrilla deposit requires relatively limited development later in the mine life, supporting lower ongoing capital requirements and significant operating flexibility.

LOM average direct production costs(2) are estimated at $109.24 per tonne processed, with cash costs(2), net of by-product credits, of $12.66 per payable oz silver and mine-site AISC(2) (including royalties and special mining duties), net of by-product credits, of $15.06 per payable oz silver.

During full years of commercial production, average annual after-tax free cash flow(1) is estimated at approximately $136 million.

Permitting, Environmental and Social Considerations

Pitarrilla has key permits in place for water use and discharge, explosives, change of land use, and underground mining and development under an Environmental Impact Statement. The Company is advancing the additional approvals, amendments and extensions required to reflect the final feasibility design, including the selected tailings-storage facility and related surface infrastructure. Endeavour will continue engagement with local communities, landholders and government authorities as the Project advances.

Opportunities to Unlock Further Value

Resource Conversion and Mine-Life Extension: Convert additional Inferred Mineral Resources to higher-confidence categories through targeted drilling and evaluate opportunities to incorporate suitable material into future mine plans. The current mine plan is based on a 150 g/t cut-off grade. A sustained higher metal price environment could support a lower cut-off grade, potentially extending mine life significantly by incorporating additional mineralized material with grades modestly below those included in the current mine plan  

Metallurgical Evaluation: The feasibility study mine plan excludes 18.4 million tonnes of mineral resources within the transition zone. This represents a significant opportunity to further evaluate the metallurgical characteristics of this material and potentially incorporate these resources into future mine plans, leveraging existing infrastructure with minimal additional mine development requirements

Exploration Upside: Test extensions of the Pitarrilla mineralization, in feeder structures which remains open at depth, and other priority targets across the property that could add higher-grade tonnes or extend the production profile

Future Open-Pit Potential: The underground sulphide strategy preserves the broader resource base, maintaining the potential to evaluate future open-pit development of Indicated and Inferred Mineral Resources, providing an additional pathway for long-term growth and value creation

Advancing Toward a Construction Decision

Endeavour is advancing Pitarrilla toward a construction decision through detailed engineering, procurement planning and project optimization, while progressing the outstanding TSF permit. With its planned long-life production and attractive cost profile, Pitarrilla represents a compelling opportunity to expand Endeavour’s silver production and create lasting shareholder value. Advancing the Project offers a platform for the Company’s next phase of organic growth.

Next steps include:

Finalize and file the supporting NI 43-101 technical report within the applicable filing period

Advance front end engineering, detailed engineering, procurement planning including long lead and major equipment commitments, and optimization opportunities

Progress outstanding TSF permit and amendments, including approvals associated with final site and tailings-facility designs

Continue community and government engagement and prepare the Project for a potential development decision, subject to Board approval and customary conditions.

Conference Call and Webcast

Management will host a conference call and webcast on Friday, November 20, 2026 at 9:00 a.m. Pacific Time (British Columbia) / 11:00 a.m. Eastern Standard Time to discuss the Feasibility Study. Following management’s presentation, there will be a question-and-answer session on the conference call line.

Date: Friday, November 20, 2026

Time: 9:00 a.m. Pacific Time (British Columbia) / 11:00 a.m. Eastern Standard Time.

Telephone: Canada & US +1-833-752-3348

International +1-647-846-2804

Webcast: Webcast link here

             

Qualified Persons and Technical Report

The Mineral Resource Estimate was prepared by the following qualified persons. Allan Armitage, Ph.D., P.Geo., of SGS Geological Services. Dr. Armitage completed site visits to the Project on April 14 and 15, 2024, September 23 and 24, 2025 and again on April 12 and 13, 2026. William van Breugel, P. Eng. is an associate engineer of SGS Geological Services, having responsibility for the project economics including capital expenditures, operating expenditures, financials and sensitivities. Johnny Canosa, P. Eng. of SGS Geological Services, having responsibility for the infrastructure, environment, permitting and social or community impact. Henri Gouin, P. Eng. of SGS Geological Services, having responsibility for the mining methods, underground mining planning and schedule. Mr. Gouin conducted a site visit on October 22 and 23, 2024. Shaohai Yu, P. Eng of SGS North America, having responsibility for the mineral processing, metallurgical testing and recovery methods. Mr. Yu conducted a site visit on September 23 and 24, 2025. Diego Cobos, PhD, of SRK Consulting (Colombia), having responsibility for the design of the tailings storage facility and associated water management structures. Mr. Cobos visited the project on 19-22 November 2024 and 16-18 March 2025.

All listed qualified persons are independent Qualified Persons as defined by NI 43-101.

The Company expects to file a technical report supporting the Study on SEDAR+ within 45 days of this news release.

Non-IFRS Financial Measures

The Company has included certain non-IFRS measures in this document as discussed below.  The Company believes that these measures, in addition to conventional measures prepared in accordance with IFRS, provide investors an improved ability to evaluate the underlying performance of the Company.  The non-IFRS measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.  These measures do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers.

Please see the September 30, 2026 MD&A for explanations and discussion of these non-IFRS and other non-financial measures and ratios. Certain additional disclosures for these non-IFRS measures have been incorporated by reference and can be found in the section “Non-IFRS Measures” in the September 30, 2026 MD&A available on SEDAR+ at www.sedarplus.com.

Cash cost (“Cash cost”) per ounce

Cash cost per ounce is a non-IFRS measure.  In the silver mining industry, this metric is a common performance measure that does not have a standardized meaning under IFRS.  Cash costs include direct costs (including smelting, refining, transportation and selling costs), royalties and special mining duty and changes in finished goods inventory net of by-product credits. 

Mine Site - All-in sustaining costs (“MAISC”) and All-in sustaining cost (“AISC”) per ounce

MAISC and AISC per ounce are non- IFRS measures.  These measures are intended to assist readers in evaluating the total cost of producing silver from operations.  While there is no standardized meaning across the industry for AISC measures, the Company’s definition conforms to the definition of AISC as set out by the World Gold Council and used as a standard of the Silver Institute.  The Company defines AISC as the cash operating costs (as defined above), reclamation cost accretion, mine site expensed exploration, corporate general and administration costs and sustaining capital expenditures. For the purpose of this press release, MAISC does not include corporate general and administration costs or mine site expensed exploration.

Free cash flow

In the mining industry, free cash flow is a common performance measure with no standardized meaning.  The Company calculates free cash flow by deducting cash capital spending (capital expenditures, net of expenditures paid through finance leases) from net cash provided by operating activities.

The Company discloses free cash flow as it believes the measure provides valuable assistance to investors and analysts in evaluating the Company’s ability to generate cash flow after capital investments and build the cash resources of the Company.

Initial and sustaining capital

Initial and sustaining capital are non-IFRS measures.  Initial capital is defined as capital required to develop and construct to bring the mine to commercial production and sustaining capital is defined as the capital required to maintain operations at existing levels.  Both measurements are used by management to assess the effectiveness of an investment program.

Earnings before Interest, Taxes, Depreciation, and Amortization (“EBITDA”)

EBITDA represents net earnings before interest, taxes, depreciation and amortization.  EBITDA is an indicator of the Company’s ability to generate liquidity by producing operating cash flow to fund working capital needs, service debt obligations, and fund capital expenditures.

Gross revenue and Gross Cost of Sales

Gross revenue represents gross sales of metals and is calculated by adjusting net revenue for the removal of treatment, refining and transportation costs.  Gross cost of sales is calculated by adjusting cost of sales for the inclusion of treatment, refining and transportation costs. 

About Endeavour Silver

Endeavour is a mid-tier silver producer with three operating mines in Mexico and Peru and a robust pipeline of exploration projects across Mexico, Chile, and the United States. With a proven track record of discovery, development, and responsible mining, Endeavour is driving organic growth and creating lasting value on its path to becoming a leading senior silver producer.

Contact Information

Allison Pettit

Vice President, Investor Relations

Email: apettit@edrsilver.com

Website: www.edrsilver.com

In Europe

Swiss Resource Capital AG

Marc Ollinger

info@resource-capital.ch

www.resource-capital.ch

Cautionary Note Regarding Forward-Looking Statements

This news release contains “forward-looking statements” within the meaning of the United States private securities litigation reform act of 1995 and “forward-looking information” within the meaning of applicable Canadian securities legislation. Such forward-looking statements and information herein include but are not limited to statements regarding planned annual production, anticipated revenue from silver, proposed operations, processing and mine plan at Pitarrilla, areas of focus at Pitarrilla, mine life, mineral resource and mineral reserve estimates, the filing of a technical report and related timing, the ability of the Company to fund construction at Pitarrilla and the sources of funding, opportunities to unlock value, the potential for Pitarrilla to become a cornerstone asset creating lasting value, organic growth, continued engagement with local stakeholders by the Company, a construction decision at Pitarrilla and planned next steps. The Company does not intend to and does not assume any obligation to update such forward-looking statements or information, other than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, production levels, performance or achievements of Endeavour and its operations to be materially different from those expressed or implied by such statements. Such risk factors include but are not limited to risks associated with mineral exploration and production, adverse changes in commodity prices, risks and delays in receiving the required licences and permits, changes in applicable laws, regulations or permitting requirements, opposition from the community and other third-party stakeholders, the ability of the Company to obtain necessary funding on acceptable terms, or at all, as well as those factors described in the section “risk factors” contained in the Company’s most recent form 40F/Annual Information Form filed with the S.E.C. and Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to: the assumptions underlying the Feasibility Study, the ability of the Company to obtain necessary funding, the continued operation of the Company’s mining operations, the ability of the Company to obtain required permits and approvals and such other assumptions and factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements or information, there may be other factors that cause results to be materially different from those anticipated, described, estimated, assessed or intended. There can be no assurance that any forward-looking statements or information will prove to be accurate as actual results and future events could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking statements or information.

Replay:Canada/US Toll Free +1-855-669-9658

International +1-412-317-0088

Access code is 4104872; audio replay will be available on the Company’s website

Mineral Reserves and Mineral Resources

The Study includes updated Mineral Reserve and Mineral Resource estimates incorporating revised mine design, mining methods, dilution and recovery assumptions. Completion of the Pitarrilla Mineral Reserve and Mineral Resource estimates involved the assessment of an updated drill hole database, which included all data for surface and underground drilling completed through October 2025.