Titlis Tower, Titlis/Engelberg
Bielefeld, 24.11.2026 (PresseBox) - An iconic observation tower designed by Herzog & de Meuron is being constructed alongside a new cable car station on Mount Titlis. In addition to a terrace, it also houses a bar and restaurant. Continuous floor-to-ceiling window fronts from Schüco allow the stunning panoramic views to be experienced in their full glory all year round.
The summit of Mount Titlis is one of the most famous tourist destinations in Switzerland. The existing cable car station, at an elevation of approx. 3000 metres above sea level, is accessible from Engelberg via the Rotair revolving cable car. Around 300 metres away from this, an approx. 50-metre-high telecommunications tower from the 1980s rises up from the summit.
Construction work is currently in full swing on Mount Titlis. Based on the comprehensive master plan by architectural practice Herzog & de Meuron from Basel, the telecommunications tower has undergone a structural transformation and has been converted for a new tourist attraction. This will be followed by the construction of a new building to replace the existing cable car station.
Logistical challenges
Building in a high alpine location follows its own set of rules. The active construction period is limited to the snow and ice-free months from April to the end of October. During this tight timeframe, the work must be carried out under intense pressure and with maximum efficiency. Even then, extreme weather conditions such as strong winds, very low temperatures, snowfall, intense solar radiation or sudden storms can significantly impact the progress of the building project.
Added to this are considerable logistical challenges. All of the material, components and machines have to be transported to the summit – or, in the case of dismantling, brought back down to the valley. Between 2024 and 2029, around 40,000 tonnes of demolition waste will be generated and will need to be removed, while 70,000 tonnes of new construction material will be transported to an elevation of approx. 3000 metres. The limited space on site and the weight limits of the cable cars require logistics to be meticulously coordinated. All of the components are supplied just-in-time in hundreds of individual deliveries. From the arrival point at the cable car station, onward transportation to the telecommunications tower about 300 metres away is carried out via all-terrain tracked vehicles. If the weather cooperates, façade units with a maximum dynamic load of 2200 kilograms are flown in by helicopter.
The telecommunications tower
The telecommunications tower built by the Swiss Postal Service in the 1980s is a striking steel structure that has been a defining feature of the skyline at the summit of Mount Titlis for decades. Following the designs of Herzog & de Meuron, the mighty infrastructure building has undergone an architectural transformation. Two glazed, steel-framed volumes that overlap in a cross-shaped pattern have been inserted into the existing load-bearing structure. The upper beam-like body will provide space for a new restaurant and bar accommodating around 120 guests. Underneath this, watch retailer Bucherer will open a boutique. In future, access will be via a new lift, which takes guests directly to the so-called Titlis Tower and then on to the observation deck beyond.
The load-bearing steel structures of the horizontally cantilevered building sections are sealed on the inside by a glazed façade. To be able to withstand the extreme climate conditions in this high-alpine location, special profiles from the Schüco AWS window portfolio are used. This system meets the highest structural requirements while also offering a high degree of architectural freedom. As part of the Schüco AWS (Aluminium Window System) modular system, this solution enables a wide variety of designs to be created, just like the floor-to-ceiling ribbon windows on Titlis Tower. From a technical point of view, the system stands out thanks to its impressive wind load resistance, maximum airtightness, triple glazing and optimised sound reduction. The system is therefore ideal for the extreme conditions on Mount Titlis, such as freezing rain, hurricane-force winds, intense solar radiation and Arctic temperatures. At 3,030 metres above sea level, Titlis Tower was fully completed on time at the end of May 2026.
Crystalline peak station
As the final step, the new cable car station will be constructed between 2026 and 2029. Its crystal-like envelope will consist of a unitised façade constructed using aluminium profiles and triple glazing. Profile systems from Schüco will also be used here. The Titlis Tower and Titlis Peak Stationproject is currently one of the highest-altitude mountain construction sites in Europe – a milestone in contemporary architecture under extreme topographical and climatic conditions.
Project details
Area of application:
Floor-to-ceiling window fronts
Products: Special profiles based on Schüco AWS 90.SI
Completion date: Spring 2026
Architecture: Herzog & de Meuron, Basel
Metal fabrication: Aepli Metallbau AG
Client: Bergbahnen Engelberg-Trübsee-Titlis AG
Ansprechpartner
Ute Minartz
+49 (521) 783-6307
+49 (521) 783-9506307
Zuständigkeitsbereich: Pressereferentin
Über SCHÜCO International KG:
Schüco – System solutions for windows, doors and façades
Based in Bielefeld, the Schüco Group develops and sells system solutions made of aluminium, steel and PVC-U for the building envelope. The product portfolio includes window, door, façade, ventilation, security and sun shading systems, as well as intelligent networked solutions for residential and commercial projects. Schüco also provides consultancy and digital solutions for all phases of a building project – from the initial idea through to design, fabrication and installation, as well as after sales with maintenance and servicing. Fabrication machinery and customer-oriented service complement the product portfolio. Founded in 1951, Schüco is now active in more than 90 countries and achieved a turnover of 2.06 billion euros in 2025 with 6750 employees.
www.schueco.com
Datei-Anlagen:
(2 MB)
1642519.attachment
Following the designs of Herzog & de Meuron, the 1980s telecommunications tower is now undergoing an architectural transformation. Two glazed, steel-framed volumes that overlap in a cross-shaped pattern have been inserted into the existing load-bearing structure
(594 kB)
1642521.attachment
The load-bearing steel structures of the horizontally cantilevered building sections were sealed on the inside by a glazed façade. The beam-like bodies provide space for a new restaurant and bar. To withstand the extreme climate conditions in this high-alpine location, special profiles from the Schüco AWS window portfolio were used
(3 MB)
1642522.attachment
The load-bearing steel structures of the horizontally cantilevered building sections were sealed on the inside by a glazed façade. The beam-like bodies provide space for a new restaurant and bar. To withstand the extreme climate conditions in this high-alpine location, special profiles from the Schüco AWS window portfolio were used
(3 MB)
1642523.attachment
The beam-like bodies in the converted telecommunications tower provide space for a new restaurant and bar accommodating around 120 guests. Access is via a new lift, which takes guests directly to the so-called Titlis Tower
(3 MB)
1642524.attachment
The beam-like bodies in the converted telecommunications tower provide space for a new restaurant and bar accommodating around 120 guests. Access is via a new lift, which takes guests directly to the so-called Titlis Tower
- Mehr Infos zu dieser Meldung unter www.pressebox.de
- zurück zur Übersicht